Notices

Hornung Field Update

Hornung Field is being prepared for turf and regrade. There is currently a pile of dirt on the field that will be flattened and smoothed out before the turfing and regrading process occurs. This work will be completed by the first week of October 2018.

0
0

New Signage is Posted

The signs that you may have seen around the park are updated. The signage gets changed every 90 days to keep the community informed of what is happening in the construction project. See updated signage below.

 

0
0

W. Broadway Parking Lot Reroute

Beginning as early as the week of July 2nd, access will be closed from Broadway and Southwestern Parkway through late December 2018. Access to the common parking lot area near W. Broadway properties will be rerouted as shown below. Residents will access the parking lot using a temporary paved road accessible through the park. Just enter the park from Broadway as usual and follow the signs.

Construction activities in this area are in support of MSD’s Shawnee Park Basin Project and this work is required to redirect combined sewer overflows from the river to the new basin currently under construction in Shawnee Park.

0
0

Meeting Notice 5.8.18

This serves as notification for the start of construction at the end of W. Broadway near the TARC turn around adjacent to Shawnee Park.

Beginning in early May, Construction activities in support of MSD’s Shawnee Park Basin Project will begin near the TARC turn around. These construction activities consist of utility relocations (i.e. water, sanitary, gas and electric). Access for residence will be maintained during these construction activities. TARC buses will be rerouted.

Tuesday, May 8, 2018 • 6:00 PM

Yearlings Club

4309 W Broadway, Louisville, KY 40211

0
0

New Signage is Posted

The signs that you may have seen around the park are updated. The signage gets changed every 90 days to keep the community informed of what is happening in the construction project. See updated signage below.

0
0

Bus Route Detour Nov. 15 – Dec. 31, 2018

November 14, 2017

Due to construction at the Shawnee Park Loop, Routes #23 & #25 will detour as follows:

 

Route #23

Westbound– From Broadway and 42nd St., bus will turn left on 44th Street, right on Garland Avenue, right on 45th Street, right on Broadway, then stop on Broadway at 44th Street.

Bus Stops Missed: From 44th Street to Shawnee Park, East and Westbound

Nearest stop: 44th Street and Broadway

 

Eastbound-From 44th St. and Broadway bus will continue regular route Eastbound.

Bus Stops Missed: From Shawnee Park Loop to 44th Street and Broadway

Nearest Stop: 44th Street and Broadway

 

Route #25
Westbound-From Southwestern Parkway, bus will turn right on Garland Avenue, left on 45th Street, right on Broadway, then stop on Broadway at 44th Street.

Bus Stops Missed: Southwestern Parkway and Shawnee Park Loop

Nearest Stop: 44th Street and Broadway and Southwestern Parkway, East and Westbound

 

Eastbound – From 44th Street and Broadway, bus will turn right on 44th Street, right on Garland Avenue, left on Southwestern Parkway to regular route.

Bus Stops Missed: Shawnee Park Loop to Garland Avenue

Nearest Stop: 44th Street and Broadway

 

0
0

Pile Driving Completed

As of Tuesday, August 29, the pile driving is complete. The noises that accompanied the pile driving, which consisted of loud booms, will be subsiding. From now on you can expect the regular construction noises as normal.

If you have questions or concerns, please contact the Shawnee Park Basin Project team at 884-429-5817 or via the site here.